Rogers Creek BESS
100.33 MW storage in Cherokee, TX · In queue since May 2023 · Proposed COD April 2028
100.33 MW
Capacity
1
Components
Battery
3 years
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-19
The Rogers Creek BESS project is a proposed 100.33 MW battery storage project located in Cherokee County, Texas. Developed by Dialville BESS, the project entered the ERCOT interconnection queue as entry ERCOT-25INR0414 on May 15, 2023. The current proposed commercial operation date is April 19, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The project consists of a single 100.33 MW battery component. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
TX
County
Cherokee
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Dialville BESS
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 KV DailVille (3160) - Neches Pump (3296)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Rogers Creek BESS