Mesa View Storage
251.3 MW storage in Upton, TX · In queue since April 2023 · Proposed COD June 2027
251.3 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-15
Mesa View Storage is a proposed 251.3 MW battery storage project located in Upton County, Texas. The project, developed by Mesa View Storage, LLC, is currently in the ERCOT interconnection queue as entry ERCOT-25INR0417, with a queue entry date of April 19, 2023. The proposed commercial operation date is June 15, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.
The Mesa View Storage project has been the subject of recent news coverage, with six articles related to the project appearing in the news. These articles cover topics such as deals, industry trends, and project development.
Generated from interconnection queue and public data sources
State
TX
County
Upton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Mesa View Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV KINGMTSW (#842) to NORTMC (#76000)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26