Bronc Rodeo Solar Project
121.63 MW generation in Falls, TX · In queue since May 2023 · Proposed COD April 2028
121.63 MW
Capacity
1
Components
Solar
3 years
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-17
The proposed Bronc Rodeo Solar Project is a 121.63 MW solar generation project located in Falls County, Texas. Developed by Energiekontor US Texas SP 16 LLC, the project consists of 121.63 MW of solar photovoltaic generation.
The project is currently in the ERCOT interconnection queue as entry ERCOT-25INR0440, with a queue entry date of May 3, 2023. Its proposed commercial operation date is April 17, 2028, and its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is the Tap 138 kV Line from Temple Pecan Creek (#3420) to the Cow Bayou Switch (#3385).
Generated from interconnection queue and public data sources
State
TX
County
Falls
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Energiekontor US Texas SP 16 LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV Line from Temple Pecan Creek (#3420) to the Cow Bayou Switch (#3385)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.