Dios BESS
201.08 MW storage in Jackson, TX · In queue since May 2023 · Proposed COD December 2027
201.08 MW
Capacity
1
Components
Battery
3 years
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
The Dios BESS project is a proposed 201.08 MW battery storage project located in Jackson County, Texas. Developed by Dios BESS, LLC, the project consists entirely of battery storage. It is currently in the ERCOT interconnection queue as entry ERCOT-25INR0441, with a queue entry date of May 15, 2023, and a proposed commercial operation date of December 31, 2027. The project's interconnection agreement status is currently in the Facility Study phase.
The Dios BESS project is linked to an existing operating facility, Dios BESS, LLC (EIA ID 67918). The point of interconnection is the 8117 GANADO138kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Jackson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Dios BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8117 GANADO138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- POI Substation
- Ganado Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.