Crowded Star I BESS
202.69 MW storage in Jones, TX · In queue since August 2023 · Proposed COD July 2027
202.69 MW
Capacity
1
Components
Battery
2y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-09
The Crowded Star I BESS project is a proposed 202.69 MW battery storage project located in Jones County, Texas. Developed by Jones City Solar II, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-25INR0473. It entered the interconnection queue on August 21, 2023, and has a proposed commercial operation date of July 9, 2027. The project's interconnection status is currently in the Facility Study phase.
The Crowded Star I BESS development has been the subject of recent news coverage, with four articles published related to deals, regulatory matters, and industry news.
Generated from interconnection queue and public data sources
State
TX
County
Jones
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Jones City Solar II, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
68014 Open Sky
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26