Solheim Solar
108.68 MW generation in Bosque, TX · In queue since August 2023 · Proposed COD November 2027
108.68 MW
Capacity
1
Components
Solar
2y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-11-01
The Solheim Solar project is a proposed 108.68 MW solar generation facility in Bosque County, Texas. Developed by Solheim Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0474, with a queue entry date of August 14, 2023. The proposed commercial operation date is November 1, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Meridian (Bus# 315) - Glen Rose (Bus #319) 69 kV line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Bosque
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Solheim Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Meridian (Bus# 315) - Glen Rose (Bus #319) 69 kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Solheim Solar