Bell Creek BESS
200.9 MW storage in Brazoria, TX · In queue since June 2023 · Proposed COD October 2027
200.9 MW
Capacity
1
Components
Battery
2y 11m
In Queue
IA Executed
IA Status
Signed Nov 2024
Queue → IA
1y 5m
IA → COD
2y 11m
Total Duration
1y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-10-30
The Bell Creek BESS project is a proposed 200.9 MW battery storage project located in Brazoria County, Texas. Developed by BELL CREEK BESS, LLC, the project consists entirely of battery storage. It is interconnected within the ERCOT region under queue ID ERCOT-25INR0480, with a queue entry date of June 28, 2023, and a proposed commercial operation date of October 30, 2027. The project's interconnection agreement has been executed as of November 14, 2024.
The proposed project is linked to the existing Bell Creek BESS LLC operating plant (EIA ID 67535). The point of interconnection is Tap 138kV 39500 West Colombia - 39703 FM524. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Brazoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BELL CREEK BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 39500 West Colombia - 39703 FM524
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- BSS_U1
- POI Substation
- Texas Pipeline Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Bell Creek BESS