Bell Creek BESS (ERCOT-25INR0480) — Project Summary

Queue ID
ERCOT-25INR0480
Capacity
200.9 MW
Technology
Battery
Status
active
Location
Brazoria, TX
Region
ERCOT
Developer
BELL CREEK BESS, LLC
IA Status
IA Executed

Bell Creek BESS

ERCOT-25INR0480BetaActiveBatteryERCOTLBNL + Live

200.9 MW storage in Brazoria, TX · In queue since June 2023 · Proposed COD October 2027

200.9 MW

Capacity

1

Components

Battery

2y 11m

In Queue

IA Executed

IA Status

Signed Nov 2024

Interconnection

Queue → IA

1y 5m

IA → COD

2y 11m

Total Duration

1y 5m

Construction75%
Queue EntryJun 28, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementNov 14, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-10-30

About

The Bell Creek BESS project is a proposed 200.9 MW battery storage project located in Brazoria County, Texas. Developed by BELL CREEK BESS, LLC, the project consists entirely of battery storage. It is interconnected within the ERCOT region under queue ID ERCOT-25INR0480, with a queue entry date of June 28, 2023, and a proposed commercial operation date of October 30, 2027. The project's interconnection agreement has been executed as of November 14, 2024.

The proposed project is linked to the existing Bell Creek BESS LLC operating plant (EIA ID 67535). The point of interconnection is Tap 138kV 39500 West Colombia - 39703 FM524. The project is currently listed as active in the interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Brazoria

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

BELL CREEK BESS, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138kV 39500 West Colombia - 39703 FM524

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
MEDIUM
Nearest Node (Estimated)
BSS_U1
POI Substation
Texas Pipeline Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Bell Creek BESS