Tarim BESS
201 MW storage in Karnes, TX · In queue since November 2024 · Proposed COD December 2027
201 MW
Capacity
1
Components
Battery
1y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
The Tarim BESS project is a proposed 201 MW battery storage project located in Karnes County, Texas. Developed by BRP Tarim BESS LLC, the project entered the ERCOT interconnection queue as entry ERCOT-25INR0491 on November 19, 2024. The proposed commercial operation date is December 1, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 5727 Pawnee Switching Substation at 138kV. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Karnes
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Tarim BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5727 Pawnee Switching Substation 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Pawnee