Willow Beach Wind
202.33 MW generation in Brazoria, TX · In queue since October 2023 · Proposed COD October 2027
202.33 MW
Capacity
1
Components
Wind
2y 7m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
4 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-01
The Willow Beach Wind project is a proposed 202.33 MW wind generation facility in Brazoria County, Texas. Developed by ACE DevCo NC LLC, the project consists of 202.33 MW of wind capacity. It is listed in the ERCOT interconnection queue as entry ERCOT-25INR0494, with a queue entry date of October 13, 2023, and a proposed commercial operation date of October 1, 2027. The project's interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing Willow Beach Wind operating plant (EIA ID 68090). Recent news coverage of the project includes regulatory matters.
Generated from interconnection queue and public data sources
State
TX
County
Brazoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
ACE DevCo NC LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV Bus# 42100 HUD_8 _x0013_ Bus# 42960 MUSTNG_S04_8 138kV CKT# 4
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- LOW
- POI Substation
- Amoco Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.