Uhland Maxwell Expansion
188.4 MW generation in Caldwell, TX · In queue since September 2023 · Proposed COD April 2026
188.4 MW
Capacity
1
Components
Gas
2y 8m
In Queue
IA Executed
IA Status
Signed Dec 2023
Queue → IA
3 months
IA → COD
2y 4m
Total Duration
3 months
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2026-04-30
The Uhland Maxwell Expansion is a proposed 188.4 MW gas-fired generation project located in Caldwell County, Texas. The developer is Lower Colorado River Authority. It is interconnected within the ERCOT region under queue ID ERCOT-25INR0503, with a queue entry date of September 22, 2023, and a proposed commercial operation date of April 30, 2026.
The project's Interconnection Agreement (IA) has been executed as of December 28, 2023. The point of interconnection (POI) is the 7041 John Dumas 345kV substation.
Generated from interconnection queue and public data sources
State
TX
County
Caldwell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Lower Colorado River Authority
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
7041 John Dumas 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Uhland Maxwell Expansion