Pearl Moon
208 MW generation in Colorado, TX · In queue since September 2023 · Proposed COD March 2028
208 MW
Capacity
1
Components
Solar
2y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-31
Pearl Moon is a proposed 208 MW solar generation project located in Colorado County, Texas. The project, developed by Pearl Moon Solar, LLC, is in the ERCOT interconnection queue as entry ERCOT-25INR0511, with a queue entry date of September 7, 2023. The proposed commercial operation date is March 31, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The Pearl Moon project consists of 208 MW of solar photovoltaic generation. The project has been mentioned in recent news coverage related to the energy industry.
Generated from interconnection queue and public data sources
State
TX
County
Colorado
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pearl Moon Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 9073 Holman - 44200 Hillje
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Holman Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.