Monument Hill Solar
200 MW generation in Fayette, TX · In queue since October 2023 · Proposed COD June 2029
200 MW
Capacity
1
Components
Solar
2y 7m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
5y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-30
Monument Hill Solar is a proposed 200 MW solar generation project located in Fayette County, Texas. The project, being developed by RWE Solar Development, LLC, is interconnected within the ERCOT region under queue ID ERCOT-25INR0512. It entered the interconnection queue on October 13, 2023, and has a proposed commercial operation date of June 30, 2029. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists of 200 MW of solar photovoltaic generation. Interconnection will occur at Tap 345kV 7055 Fayette - 9074 Lytton Springs. The project has been mentioned in recent news coverage related to the electric grid.
Generated from interconnection queue and public data sources
State
TX
County
Fayette
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
RWE Solar Development, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 7055 Fayette - 9074 Lytton Springs
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- FPPYD_FPP_G1
- POI Substation
- Fayette Plant #1 Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Monument Hill Solar