Port City Energy Storage
101.2 MW storage in San Patricio, TX · In queue since October 2023 · Proposed COD June 2026
101.2 MW
Capacity
1
Components
Battery
2y 7m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
2y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-15
The Port City Energy Storage project is a proposed 101.2 MW battery storage project located in San Patricio County, Texas. Developed by Port City Energy Storage, LLC, the project entered the ERCOT interconnection queue as entry ERCOT-25INR0541 on October 25, 2023. The current interconnection status is listed as Facility Study, with a proposed commercial operation date of June 15, 2026.
The project consists entirely of battery storage, with a total capacity of 101.2 MW. The point of interconnection is Tap 138kV 80258 Mayo4A - 80260 Gila4A. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
San Patricio
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Port City Energy Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 80258 Mayo4A - 80260 Gila4A
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Port City Energy Storage