Dan Kearney BESS
200.78 MW storage in Brazoria, TX · In queue since January 2024 · Proposed COD October 2027
200.78 MW
Capacity
1
Components
Battery
2y 4m
In Queue
IA Executed
IA Status
Signed Oct 2024
Queue → IA
9 months
IA → COD
3 years
Total Duration
9 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-10-01
The Dan Kearney BESS project is a proposed 200.78 MW battery storage project located in Brazoria County, Texas. The developer is Dan Kearney BESS LLC. It is interconnected within the ERCOT region under queue ID ERCOT-25INR0554.
The project entered the interconnection queue on January 11, 2024, and has a proposed commercial operation date of October 1, 2027. The Interconnection Agreement (IA) for the project has been executed as of October 18, 2024.
Generated from interconnection queue and public data sources
State
TX
County
Brazoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Dan Kearney BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
39703 TNFM524 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Dan Kearney BESS