Stargazer Solar
157.7 MW generation in Brazoria, TX · In queue since October 2023 · Proposed COD February 2027
157.7 MW
Capacity
1
Components
Solar
2y 7m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-02-01
The Stargazer Solar project is a proposed 157.7 MW solar generation facility located in Brazoria County, Texas. The project, developed by Stargazer Solar LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0555, with a queue entry date of October 30, 2023. The proposed commercial operation date is February 1, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 44010 WA Parish - 42980 Nash 138 kV Ckt 02. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Brazoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Stargazer Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
44010 WA Parish - 42980 Nash 138 kV Ckt 02
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.