Zeus Armstrong Solar (ERCOT-25INR0586) — Project Summary

Queue ID
ERCOT-25INR0586
Capacity
509.6 MW
Technology
Solar
Status
active
Location
Armstrong, TX
Region
ERCOT
Developer
Armstrong Solar, LLC
IA Status
Facility Study

Zeus Armstrong Solar

ERCOT-25INR0586BetaActiveSolarERCOTLBNL + Live

509.6 MW generation in Armstrong, TX · In queue since May 2024 · Proposed COD April 2028

509.6 MW

Capacity

1

Components

Solar

2 years

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection

Total Duration

3y 11m

Facilities Study50%
Queue EntryMay 20, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-17

About

The Zeus Armstrong Solar project is a proposed solar generation facility with a total capacity of 509.6 MW. It is located in Armstrong County, Texas, and is being developed by Armstrong Solar, LLC. The project is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0586, with a queue entry date of May 20, 2024.

The proposed commercial operation date for the Zeus Armstrong Solar project is April 17, 2028. Its interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 345KV 23900 AlLIBATES -23914 TULECNYN. The project has appeared in recent news.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Armstrong

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Armstrong Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 345KV 23900 AlLIBATES -23914 TULECNYN

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.