Adam Bryant BESS
99.9 MW storage in Medina, TX · In queue since February 2024 · Proposed COD December 2027
99.9 MW
Capacity
1
Components
Battery
2y 3m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
The Adam Bryant BESS project is a proposed 99.9 MW battery storage project located in Medina County, Texas. The project, developed by Adam Bryant BESS LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0610, with a queue entry date of February 26, 2024. The proposed commercial operation date is December 1, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.
The project consists of 99.9 MW of battery storage capacity. The point of interconnection is Tap 138kV 5225 HONDO _x0013_ 5819 HONDO CREEK. The Adam Bryant BESS project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Medina
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Adam Bryant BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 5225 HONDO _x0013_ 5819 HONDO CREEK
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Adam Bryant BESS