Carolina Storage Odessa
202.05 MW storage in Howard, TX · In queue since February 2024 · Proposed COD May 2029
202.05 MW
Capacity
1
Components
Battery
2y 3m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-05-01
The Carolina Storage Odessa project is a proposed 202.05 MW battery storage project located in Howard County, Texas. Developed by CSE STORAGE, LLC, the project entered the ERCOT interconnection queue as entry ERCOT-25INR0611 on February 2, 2024. The proposed commercial operation date is May 1, 2029, and the project's interconnection status is currently in the Facility Study phase.
The development has been the subject of recent news coverage, with four articles focusing on grid issues, deals, and industry trends. The point of interconnection is the 1058 LONGSHORE 345kV.
Generated from interconnection queue and public data sources
State
TX
County
Howard
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
CSE STORAGE, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1058 LONGSHORE 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- PC_NORTH_1
- POI Substation
- Longshore Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26