Anagram Solar
130.56 MW generation in Live Oak, TX · In queue since April 2024 · Proposed COD December 2027
130.56 MW
Capacity
1
Components
Solar
2y 1m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
Anagram Solar is a proposed 130.56 MW solar generation project located in Live Oak County, Texas. The development project, sponsored by Anagram Solar, entered the ERCOT interconnection queue as ERCOT-25INR0621 on April 9, 2024. Its proposed commercial operation date is December 31, 2027. The project's interconnection status is currently in the Facility Study phase.
The Anagram Solar project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Live Oak
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Anagram Solar
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8156 Charter 138 kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Anagram Solar