Turkey Creek Solar
211.2 MW generation in Kinney, TX · In queue since February 2024 · Proposed COD October 2027
211.2 MW
Capacity
1
Components
Solar
2y 3m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-26
The Turkey Creek Solar project is a proposed 211.2 MW solar generation facility in Kinney County, Texas. The project, being developed by Greenray Solar Corporation, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0622, with a queue entry date of February 26, 2024. The proposed commercial operation date is October 26, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.
The proposed project consists of 211.2 MW of solar photovoltaic generation. The point of interconnection is the 7425 ODLASW 138kV substation. The Turkey Creek Solar project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Kinney
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Greenray Solar Corporation
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
7425 ODLASW 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Turkey Creek Solar