Jenna Eco-Electric Solar
576.3 MW generation in Fisher, TX · In queue since May 2024 · Proposed COD April 2028
576.3 MW
Capacity
1
Components
Solar
2 years
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-19
The Jenna Eco-Electric Solar project is a proposed 576.3 MW solar generation facility in Fisher County, Texas. Being developed by Clean Energy Holdings, LLC, the project entered the ERCOT interconnection queue as ERCOT-25INR0632 on May 20, 2024. Its proposed commercial operation date is April 19, 2028, and its interconnection status is currently in the Facility Study phase.
The development project consists solely of solar photovoltaic generation. Recent news coverage indicates industry interest in the Jenna Eco-Electric Solar project.
Generated from interconnection queue and public data sources
State
TX
County
Fisher
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Clean Energy Holdings, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 1048 Tonkawa Switch - 1430 Graham SES
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the powerplantsinfo.org database.
Compare Texas vs California solar
Summary analysis with parallel narrative sections and visualizations.
Top 10 solar states
Data tables and metrics from the powerplantsinfo.org database.