Gilleys Energy Storage (ERCOT-25INR0656) — Project Summary

Queue ID
ERCOT-25INR0656
Capacity
306.4 MW
Technology
Battery
Status
active
Location
Wise, TX
Region
ERCOT
Developer
Gilleys Energy Storage, LLC
IA Status
Facility Study

Gilleys Energy Storage

ERCOT-25INR0656BetaActiveBatteryERCOTLBNL + Live

306.4 MW storage in Wise, TX · In queue since June 2024 · Proposed COD April 2028

306.4 MW

Capacity

1

Components

Battery

1y 11m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection

Total Duration

3y 10m

Facilities Study50%
Queue EntryJun 3, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-21

About

The Gilleys Energy Storage project is a proposed 306.4 MW battery storage facility in Wise County, Texas. The project, developed by Gilleys Energy Storage, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0656, with a queue entry date of June 3, 2024. The proposed commercial operation date is April 21, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.

The point of interconnection for the project is Tap 345 kV 1730 West Krum - 6111 Riley CKT 2. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Wise

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Gilleys Energy Storage, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 345 kV 1730 West Krum - 6111 Riley CKT 2

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
HMNG_ESS_RN
POI Substation
West Krum Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.