McCrae Energy Storage
306.35 MW storage in Erath, TX · In queue since May 2024 · Proposed COD September 2028
306.35 MW
Capacity
1
Components
Battery
2 years
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-25
The McCrae Energy Storage project is a proposed 306.35 MW battery storage project located in Erath County, Texas. The project is being developed by McCrae Energy Storage, LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-25INR0661, with a queue entry date of May 20, 2024.
The proposed commercial operation date for the McCrae Energy Storage project is September 25, 2028. Its interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 345 kV 1900 COMCHPKW_5 - 1440 COMCHESS1_5.
Generated from interconnection queue and public data sources
State
TX
County
Erath
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
McCrae Energy Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 1900 COMCHPKW_5 - 1440 COMCHESS1_5
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.