Fagus Solar Park 2 SLF
166.57 MW generation in Childress, TX · In queue since June 2024 · Proposed COD March 2026
166.57 MW
Capacity
1
Components
Solar
1y 11m
In Queue
IA Executed
IA Status
Signed Feb 2019
IA → COD
7y 1m
Total Duration
1y 11m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-03-15
Fagus Solar Park 2 SLF is a proposed solar generation project located in Childress County, Texas, within the ERCOT region. The project, developed by Excel Advantage Services, LLC dba Misae Solar Park II, has a total capacity of 166.57 MW. It consists entirely of solar photovoltaic generation.
The project is listed in the ERCOT interconnection queue as entry ERCOT-25INR0672, with a queue entry date of June 3, 2024. The proposed commercial operation date is March 15, 2026. An Interconnection Agreement (IA) has been executed for the project, with an IA execution date of February 21, 2019. The point of interconnection is the 60501 Tesla 345 kV substation.
Generated from interconnection queue and public data sources
State
TX
County
Childress
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Excel Advantage Services, LLC dba Misae Solar Park II
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60501 Tesla 345 kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- MISAE_GEN_RN
- POI Substation
- Tesla Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Fagus Solar Park 2 SLF