Leon BESS
153.7 MW storage in Houston, TX · In queue since November 2024 · Proposed COD February 2028
153.7 MW
Capacity
1
Components
Battery
1y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-02-16
The Leon BESS project is a proposed 153.7 MW battery storage project located in Houston County, Texas. The developer is listed as Leon BESS. It is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0693, with a queue entry date of November 26, 2024. The proposed commercial operation date is February 16, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tab 138kv 3355 Grapeland_Magnolia - 3357 Pleasant_Springs. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Houston
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Leon BESS
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tab 138kv 3355 Grapeland_Magnolia - 3357 Pleasant_Springs.
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Leon BESS