Compton BESS
9.95 MW storage in Dallas, TX · In queue since August 2024 · Proposed COD May 2025
9.95 MW
Capacity
1
Components
Battery
1y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
9 months
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-05-15
The Compton BESS project is a proposed 9.95 MW battery storage project located in Dallas County, Texas. Developed by SMT Dallas VII LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-25INR0699. The project entered the interconnection queue on August 29, 2024, with a proposed commercial operation date of May 15, 2025.
The interconnection agreement for the Compton BESS project is currently listed as "In Progress (unknown study)". The point of interconnection is designated as POIB 2981 ERCOT Bus name COMPTON1_8 ERCOT load name LDLXFMR1 Oncor XFMR number 1. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Dallas
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
SMT Dallas VII LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
POIB 2981 ERCOT Bus name COMPTON1_8 ERCOT load name LDLXFMR1 Oncor XFMR number 1
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- 1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Compton BESS