Abilene Elmcreek BESS (ERCOT-25INR0701) — Project Summary

Queue ID
ERCOT-25INR0701
Capacity
9.9 MW
Technology
Battery
Status
active
Location
Taylor, TX
Region
ERCOT
Developer
DGSP2 LLC
IA Status
IA Executed

Abilene Elmcreek BESS

ERCOT-25INR0701BetaActiveBatteryERCOTLBNL

9.9 MW storage in Taylor, TX · In queue since September 2024 · Proposed COD June 2025

9.9 MW

Capacity

1

Components

Battery

1y 8m

In Queue

IA Executed

IA Status

Signed Aug 2024

Interconnection

IA → COD

10 months

Total Duration

1y 8m

Schedule

10 months past proposed COD

Construction75%
Queue EntrySep 12, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementAug 15, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2025-06-30

About

The Abilene Elmcreek BESS is a proposed 9.9 MW battery storage project located in Taylor County, Texas. Developed by DGSP2 LLC, the project is interconnected within the Electric Reliability Council of Texas (ERCOT) queue as entry ERCOT-25INR0701, with a queue entry date of September 12, 2024. The project's proposed commercial operation date is June 30, 2025.

The Abilene Elmcreek BESS project has an Interconnection Agreement (IA) executed as of August 15, 2024. The point of interconnection is the Abilene Elm Creek station, specifically the LOAD1 load transformer on Bus #6255 at 138kV. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Taylor

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

DGSP2 LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Station Name: Abilene Elm Creek TSP Station Code: ELMCRK Load Transformer name: LOAD1 Bus#: 6255 Voltage in kV (Transmission Level): 138kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Abilene Elmcreek BESS