Abilene Elmcreek BESS
9.9 MW storage in Taylor, TX · In queue since September 2024 · Proposed COD June 2025
9.9 MW
Capacity
1
Components
Battery
1y 8m
In Queue
IA Executed
IA Status
Signed Aug 2024
IA → COD
10 months
Total Duration
1y 8m
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-06-30
The Abilene Elmcreek BESS is a proposed 9.9 MW battery storage project located in Taylor County, Texas. Developed by DGSP2 LLC, the project is interconnected within the Electric Reliability Council of Texas (ERCOT) queue as entry ERCOT-25INR0701, with a queue entry date of September 12, 2024. The project's proposed commercial operation date is June 30, 2025.
The Abilene Elmcreek BESS project has an Interconnection Agreement (IA) executed as of August 15, 2024. The point of interconnection is the Abilene Elm Creek station, specifically the LOAD1 load transformer on Bus #6255 at 138kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Taylor
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
DGSP2 LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Station Name: Abilene Elm Creek TSP Station Code: ELMCRK Load Transformer name: LOAD1 Bus#: 6255 Voltage in kV (Transmission Level): 138kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.