Turin TxHSR TPSS HN-6
50 MW generation in Grimes, TX · In queue since September 2019 · Proposed COD July 2028
50 MW
Capacity
1
Components
Other
6y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
8y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-15
The Turin TxHSR TPSS HN-6 project is a proposed 50 MW generation project located in Grimes County, Texas. The project, developed by Texas Central Rail Holdings, LLC, consists of 50 MW of unspecified "Other" generation technology. It is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0001, with a queue entry date of September 27, 2019.
The proposed commercial operation date for the Turin TxHSR TPSS HN-6 project is July 15, 2028. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 8 Crutchfield 138kV location.
Generated from interconnection queue and public data sources
State
TX
County
Grimes
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Texas Central Rail Holdings, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8 Crutchfield 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- FTR_CC1
- POI Substation
- Crutchfield Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.