Greenwolfe Solar Alt POI
274.14 MW generation in Hunt, TX · In queue since November 2022 · Proposed COD September 2026
274.14 MW
Capacity
1
Components
Solar
3y 6m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-24
Greenwolfe Solar Alt POI is a proposed 274.14 MW solar generation project located in Hunt County, Texas. The project, developed by EDF Renewables Development, Inc., is in the ERCOT interconnection queue as entry ERCOT-26INR0014, with a queue entry date of November 15, 2022. The proposed commercial operation date is September 24, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection (POI) is planned at the tap of the 345 kV line from Farmersville Switch (#1685) to Cyclone Switch (#11689). The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Hunt
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
EDF Renewables Development, Inc.
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV line from Farmersville Switch (#1685) to Cyclone Switch (#11689)
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Greenwolfe Solar Alt POI