HyFuels Green Lake Solar
346 MW generation in Victoria, TX · In queue since September 2022 · Proposed COD December 2027
346 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
The HyFuels Green Lake Solar project is a proposed 346 MW solar generation project located in Victoria County, Texas. The developer is HyFuels Green Lake Solar LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0019, with a queue entry date of September 27, 2022. The proposed commercial operation date is December 1, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 8189 Tungsten 138kV location. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Victoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
HyFuels Green Lake Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8189 Tungsten 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.