Leon Solar Park
210.1 MW generation in Leon, TX · In queue since September 2022 · Proposed COD July 2026
210.1 MW
Capacity
1
Components
Solar
3y 8m
In Queue
IA Executed
IA Status
Signed May 2024
Queue → IA
1y 8m
IA → COD
2y 2m
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-07-01
Leon Solar Park is a proposed 210.1 MW solar generation project located in Leon County, Texas. The developer is Misae Solar IV LLC. The project is in the ERCOT interconnection queue as entry ERCOT-26INR0023, with a queue entry date of September 15, 2022, and a proposed commercial operation date of July 1, 2026. The interconnection agreement was executed on May 21, 2024.
The point of interconnection is the Tap 138kV Grapeland Magnolia Tap (bus #3355) to Pleasant Springs POI (bus# 3357) section of the Jewett -Crockett 138kV Line. The project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Leon
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Misae Solar IV LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV Grapeland Magnolia Tap (bus #3355) to Pleasant Springs POI (bus# 3357) section of the Jewett -Crockett 138kV Line
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Crockett Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Leon Solar Park