Becerra Creek Storage 1
125.62 MW storage in Webb, TX · In queue since September 2022 · Proposed COD December 2027
125.62 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
The Becerra Creek Storage 1 project is a proposed 125.62 MW battery storage project located in Webb County, Texas. Developed by Bordas Renewable Energy, LLC, the project entered the ERCOT interconnection queue as entry ERCOT-26INR0024 on September 21, 2022. The current interconnection status is listed as Facility Study, with a proposed commercial operation date of December 1, 2027.
The project consists of 125.62 MW of battery storage capacity. The point of interconnection is the 345 kV Cenizo Substation (#80220). The project is currently listed as active within the ERCOT queue.
Generated from interconnection queue and public data sources
State
TX
County
Webb
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Bordas Renewable Energy, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345 kV Cenizo Substation (#80220)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Cenizo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Becerra Creek Storage 1