Bracero Pecan Storage (ERCOT-26INR0034) — Project Summary

Queue ID
ERCOT-26INR0034
Capacity
232 MW
Technology
Battery
Status
active
Location
Reeves, TX
Region
ERCOT
Developer
Bracero Pecan Storage LLC
IA Status
IA Executed

Bracero Pecan Storage

ERCOT-26INR0034BetaActiveBatteryERCOTLBNL + Live

232 MW storage in Reeves, TX · In queue since November 2022 · Proposed COD July 2027

232 MW

Capacity

1

Components

Battery

3y 6m

In Queue

IA Executed

IA Status

Signed Jun 2024

Interconnection

Queue → IA

1y 7m

IA → COD

3y 1m

Total Duration

1y 7m

Construction75%
Queue EntryNov 7, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJun 27, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-07-01

About

Bracero Pecan Storage is a proposed 232 MW battery storage project in Reeves County, Texas. Developed by Bracero Pecan Storage LLC, the project consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0034, with a queue entry date of November 7, 2022, and a proposed commercial operation date of July 1, 2027. The project's interconnection agreement has been executed as of June 27, 2024.

The point of interconnection is the 60716 SARAGOSA 138kV location. The project has been mentioned in recent industry news.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Reeves

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Bracero Pecan Storage LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

60716 SARAGOSA 138kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
MEDIUM
POI Substation
Saragosa Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Bracero Pecan Storage