Valhalla Solar
306.8 MW generation in Brazoria, TX · In queue since March 2023 · Proposed COD May 2026
306.8 MW
Capacity
1
Components
Solar
3y 2m
In Queue
IA Executed
IA Status
Signed Dec 2023
Queue → IA
9 months
IA → COD
2y 5m
Total Duration
9 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-05-31
The Valhalla Solar project is a proposed 306.8 MW solar generation facility in Brazoria County, Texas. Developed by Industrial Papa Project LLC, it is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0042, with a queue entry date of March 9, 2023. The project has a proposed commercial operation date of May 31, 2026, and an Interconnection Agreement (IA) was executed on December 6, 2023. The point of interconnection is Tap 138 kV 42215 Copper to 42195 Booster.
The Valhalla Solar project has been the subject of recent news coverage, with two articles focusing on deals related to the project.
Generated from interconnection queue and public data sources
State
TX
County
Brazoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Industrial Papa Project LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV 42215 Copper to 42195 Booster
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.