LUND STORAGE CENTER 1
407.55 MW storage in Bastrop, TX · In queue since January 2023 · Proposed COD December 2028
407.55 MW
Capacity
1
Components
Battery
3y 4m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
The Lund Storage Center 1 project is a proposed 407.55 MW battery storage project located in Bastrop County, Texas. Developed by Lund Storage Center 1, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-26INR0045. The project entered the interconnection queue on January 17, 2023, and has a proposed commercial operation date of December 31, 2028. Its interconnection status is currently in the Facility Study phase.
The development project consists solely of battery storage with a total capacity of 407.55 MW. Recent news coverage indicates industry interest in the project.
Generated from interconnection queue and public data sources
State
TX
County
Bastrop
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Lund Storage Center 1, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP 138 KV LINE AND CREATE NEW BUS BETWEEN KIMBRO (7337) AND ELGIN SWITCH (3650)