Paluxy Storage (ERCOT-26INR0047) — Project Summary

Queue ID
ERCOT-26INR0047
Capacity
511.68 MW
Technology
Battery
Status
active
Location
Victoria, TX
Region
ERCOT
Developer
S&S Renewables LLC
IA Status
Facility Study

Paluxy Storage

ERCOT-26INR0047BetaActiveBatteryERCOTLBNL

511.68 MW storage in Victoria, TX · In queue since January 2023 · Proposed COD June 2027

511.68 MW

Capacity

1

Components

Battery

3y 4m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

4y 5m

Facilities Study50%
Queue EntryJan 3, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-30

About

The Paluxy Storage project is a proposed 511.68 MW battery energy storage system in Victoria County, Texas. Developed by S&S Renewables LLC, the project consists entirely of battery storage. It is currently in the ERCOT interconnection queue as entry ERCOT-26INR0047, with a queue entry date of January 3, 2023, and a proposed commercial operation date of June 30, 2027. The project's interconnection status is currently in the Facility Study phase.

The point of interconnection (POI) is described as double tapping the 345kV 5915 STP - 5133 Elm Creek ckt#1 and 345kV 5068 Cachena _x0013_ 5323 Old Hickory ckt#2 lines. The Paluxy Storage project has been mentioned in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Victoria

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

S&S Renewables LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Double tapping: 345kV 5915 STP - 5133 Elm Creek ckt#1 and 345kV 5068 Cachena _x0013_ 5323 Old Hickory ckt#2

Data Source

LBNL

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.