Anila Solar
200.8 MW generation in Wilson, TX · In queue since January 2023 · Proposed COD June 2028
200.8 MW
Capacity
1
Components
Solar
3y 4m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
The Anila Solar project is a proposed 200.8 MW solar generation facility in Wilson County, Texas. The project, developed by Alina Energy LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0074, with a queue entry date of January 30, 2023. The proposed commercial operation date is June 30, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for Anila Solar is Tap 345kV 5133 Elm Creek - 5901 San Miguel Gen Ckt 1. The project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Wilson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Alina Energy LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 5133 Elm Creek - 5901 San Miguel Gen Ckt 1
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Elm Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.