Matias Solar
152.3 MW generation in Matagorda, TX · In queue since March 2023 · Proposed COD March 2027
152.3 MW
Capacity
1
Components
Solar
3y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
4 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-31
The Matias Solar project is a proposed 152.3 MW solar generation facility in Matagorda County, Texas. Developed by Industrial Bravo Project II LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0076, with a queue entry date of March 13, 2023. The proposed commercial operation date is March 31, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.
The project will interconnect at the 8114 Conoco 138kV point of interconnection. The Matias Solar project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Matagorda
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Industrial Bravo Project II LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8114 Conoco 138kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Conoco Substation