Amerada Solar
301.57 MW generation in Freestone, TX · In queue since May 2023 · Proposed COD December 2028
301.57 MW
Capacity
1
Components
Solar
3 years
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-30
Amerada Solar is a proposed solar generation project located in Freestone County, Texas, within the ERCOT region. The project, developed by Amerada Solar, LLC, has a total capacity of 301.57 MW. It consists entirely of solar photovoltaic generation.
The project is listed in the ERCOT interconnection queue as entry ERCOT-26INR0082, with a queue entry date of May 15, 2023, and a proposed commercial operation date of December 30, 2028. Its interconnection status is currently in the Facility Study phase. The project is linked to the existing Amerada operating plant (EIA ID 67649).
Generated from interconnection queue and public data sources
State
TX
County
Freestone
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Amerada Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 3133 RICHLND2_5 - 3381 BIGBRNW_5
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- FREC
- POI Substation
- Richland Chambers Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.