Western Flats Solar (ERCOT-26INR0110) — Project Summary

Queue ID
ERCOT-26INR0110
Capacity
410.2 MW
Technology
Solar
Status
active
Location
Crane, TX
Region
ERCOT
Developer
Hecate Energy Point Mountain Solar Facility 1 LLC
IA Status
Facility Study

Western Flats Solar

ERCOT-26INR0110BetaActiveSolarERCOTLBNL + Live

410.2 MW generation in Crane, TX · In queue since April 2023 · Proposed COD November 2028

410.2 MW

Capacity

1

Components

Solar

3y 1m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection

Total Duration

5y 7m

Facilities Study50%
Queue EntryApr 7, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-11-01

About

Western Flats Solar is a proposed 410.2 MW solar generation project located in Crane County, Texas. The project is being developed by Hecate Energy Point Mountain Solar Facility 1 LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0110, with a queue entry date of April 7, 2023, and a proposed commercial operation date of November 1, 2028. The project's interconnection status is currently in the Facility Study phase.

The proposed project consists of 410.2 MW of solar generation capacity. The point of interconnection (POI) is Tap 138 kV 76615 Crane -76635 King Mountain, located 7.85 miles from Crane. The Western Flats Solar project has been mentioned in recent industry news.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Crane

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Hecate Energy Point Mountain Solar Facility 1 LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138 kV 76615 Crane -76635 King Mountain; POI is 7.85 miles from Crane.

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
MEDIUM
POI Substation
Crane East Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.