Lemma Solar
100.61 MW generation in Knox, TX · In queue since April 2023 · Proposed COD July 2028
100.61 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
The Lemma Solar project is a proposed 100.61 MW solar generation facility in Knox County, Texas. Developed by Greening USA Corp., the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0112, with a queue entry date of April 7, 2023. The proposed commercial operation date is July 1, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The project consists of 100.61 MW of solar photovoltaic generation. The point of interconnection is the 6088 Benjamin AEP 138kV line. The Lemma Solar project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Knox
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Greening USA Corp.
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6088 Benjamin AEP 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Benjamin Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Lemma Solar