Meitner Wind
836.5 MW generation in Gray, TX · In queue since July 2023 · Proposed COD December 2027
836.5 MW
Capacity
1
Components
Wind
2y 10m
In Queue
IA Executed
IA Status
Signed Apr 2024
Queue → IA
9 months
IA → COD
3y 8m
Total Duration
9 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2027-12-20
The Meitner Wind project is a proposed 836.5 MW wind generation facility in Gray County, Texas. The developer is IP Meitner, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0113, with a queue entry date of July 18, 2023. The project's proposed commercial operation date is December 20, 2027.
The project has an executed Interconnection Agreement (IA), dated April 19, 2024. The point of interconnection (POI) is the 79000 Gray Substation 345kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Gray
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
IP Meitner, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
79000 Gray Substation 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Gray Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.