Pioneer Hutt Solar (Alternative POI)
116 MW generation in Midland, TX · In queue since June 2023 · Proposed COD July 2028
116 MW
Capacity
1
Components
Solar
2y 11m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
The Pioneer Hutt Solar (Alternative POI) project is a proposed 116 MW solar generation facility in Midland County, Texas. The project, being developed by NextEra Energy Interconnection Holdings LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0121, with a queue entry date of June 28, 2023.
The proposed commercial operation date for the Pioneer Hutt Solar (Alternative POI) project is July 1, 2028. Its interconnection status is currently in the Facility Study phase, and the Point of Interconnection (POI) is the TAP 345kV 11028 Odessa Ehv - 59901 Grelton (West C) substation.
Generated from interconnection queue and public data sources
State
TX
County
Midland
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
NextEra Energy Interconnection Holdings LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP 345kV 11028 Odessa Ehv - 59901 Grelton (West C)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- OECCS_1
- POI Substation
- Odessa EHV Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.