Elm Flats Solar SLF
125.58 MW generation in Navarro, TX · In queue since July 2024 · Proposed COD September 2027
125.58 MW
Capacity
1
Components
Solar
1y 10m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-30
The Elm Flats Solar SLF project is a proposed solar generation facility with a total capacity of 125.58 MW. Located in Navarro County, Texas, the project is being developed by Elm Flats Solar, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0130, with a queue entry date of July 30, 2024.
The proposed commercial operation date for the Elm Flats Solar SLF project is September 30, 2027. Its interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 138kV 3472 BRIAR_CRK_8 _x0013_ 3467 POWELL1_8.
Generated from interconnection queue and public data sources
State
TX
County
Navarro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Elm Flats Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 3472 BRIAR_CRK_8 _x0013_ 3467 POWELL1_8
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Elm Flats Solar SLF