Santa Garcias Solar (ERCOT-26INR0143) — Project Summary

Queue ID
ERCOT-26INR0143
Capacity
265 MW
Technology
Solar
Status
active
Location
Kleberg, TX
Region
ERCOT
Developer
Oxy Renewable Energy LLC
IA Status
Facility Study

Santa Garcias Solar

ERCOT-26INR0143BetaActiveSolarERCOTLBNL + Live

265 MW generation in Kleberg, TX · In queue since June 2023 · Proposed COD May 2028

265 MW

Capacity

1

Components

Solar

2y 11m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection

Total Duration

4y 11m

Facilities Study50%
Queue EntryJun 28, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-30

About

The Santa Garcias Solar project is a proposed 265 MW solar generation facility in Kleberg County, Texas. Developed by Oxy Renewable Energy LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0143, with a queue entry date of June 28, 2023.

The proposed commercial operation date for the Santa Garcias Solar project is May 30, 2028. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 138kV 8515 Alazan - 8458 Barney Davis.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Kleberg

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Oxy Renewable Energy LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138kV 8515 Alazan - 8458 Barney Davis

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
SANTACRU_ALL
POI Substation
Alazan Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Santa Garcias Solar