Wittig Solar
106.9 MW generation in Wharton, TX · In queue since February 2024 · Proposed COD October 2028
106.9 MW
Capacity
1
Components
Solar
2y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-30
The Wittig Solar project is a proposed solar generation facility with a total capacity of 106.9 MW, located in Wharton County, Texas. The developer is Greenalia Solar Power Wittig LLC. This project is interconnected within the ERCOT region and is listed in the ERCOT interconnection queue as entry ERCOT-26INR0144, with a queue entry date of February 27, 2024. The proposed commercial operation date is October 30, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The proposed project is linked to the existing Wittig Solar Park operating plant (EIA ID 67568). Recent news coverage has discussed this development project.
Generated from interconnection queue and public data sources
State
TX
County
Wharton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Greenalia Solar Power Wittig LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138 kV Gulftie (#43340) _x0013_ San Bernard (#43110)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SAN_SANMIGG1
- POI Substation
- Texas Gulf Sulfur Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.