Proving Ground Solar
82.1 MW generation in Schleicher, TX · In queue since July 2023 · Proposed COD June 2028
82.1 MW
Capacity
1
Components
Solar
2y 10m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
Proving Ground Solar is a proposed 82.1 MW solar generation project located in Schleicher County, Texas. The project, developed by Lantana Solar LLC, is in the ERCOT interconnection queue as entry ERCOT-26INR0150, with a queue entry date of July 10, 2023. The proposed commercial operation date is June 30, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The proposed project consists of 82.1 MW of solar capacity. Recent news coverage indicates industry interest in the development.
Generated from interconnection queue and public data sources
State
TX
County
Schleicher
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Lantana Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV Live Oak (6500) - Santiago (6490)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Proving Ground Solar