AQUAMARINE BESS
213.81 MW storage in Dickens, TX · In queue since June 2023 · Proposed COD May 2026
213.81 MW
Capacity
1
Components
Battery
2y 11m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-05-23
The AQUAMARINE BESS project is a proposed 213.81 MW battery storage project located in Dickens County, Texas. The developer is ME USA Project I LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0169, with a queue entry date of June 28, 2023, and a proposed commercial operation date of May 23, 2026. The project's interconnection status is currently in the Facility Study phase.
The point of interconnection is the tap 138kV 720 Salt Creek Reactor _x0013_ 6150 Spur. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Dickens
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
ME USA Project I LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 720 Salt Creek Reactor _x0013_ 6150 Spur
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.