Dionysus Storage (ERCOT-26INR0177) — Project Summary

Queue ID
ERCOT-26INR0177
Capacity
77.28 MW
Technology
Battery
Status
active
Location
Houston, TX
Region
ERCOT
Developer
Dionysus Solar, LLC
IA Status
Facility Study

Dionysus Storage

ERCOT-26INR0177BetaActiveBatteryERCOTLBNL + Live

77.28 MW storage in Houston, TX · In queue since June 2023 · Proposed COD March 2027

77.28 MW

Capacity

1

Components

Battery

2y 11m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

3y 9m

Facilities Study50%
Queue EntryJun 28, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-03-11

About

The Dionysus Storage project is a proposed 77.28 MW battery energy storage system in Houston County, Texas. Developed by Dionysus Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0177, with a queue entry date of June 28, 2023. The proposed commercial operation date is March 11, 2027.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 138kV 6733 Mustang Prairie - 6732 Latexo. The Dionysus Storage project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Houston

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Dionysus Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138kV 6733 Mustang Prairie - 6732 Latexo

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
POI Substation
Mustang Prairie Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Dionysus Storage