Skipjack Energy Storage
150.6 MW storage in Brazoria, TX · In queue since July 2023 · Proposed COD February 2028
150.6 MW
Capacity
1
Components
Battery
2y 10m
In Queue
IA Executed
IA Status
Signed Aug 2024
Queue → IA
1y 1m
IA → COD
3y 6m
Total Duration
1y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2028-02-28
Skipjack Energy Storage is a proposed 150.6 MW battery storage project located in Brazoria County, Texas. The developer is Skipper Energy Storage LLC. The project is in the ERCOT interconnection queue as entry ERCOT-26INR0189, with a queue entry date of July 31, 2023, and a proposed commercial operation date of February 28, 2028. The interconnection agreement (IA) has been executed as of August 13, 2024.
The proposed project consists of 150.6 MW of battery storage capacity. Skipjack Energy Storage has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Brazoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Skipper Energy Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 42980 Nash - 44010 W A Parish ckt #2
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.